The rectification method and Corrective Action are completed in the “Rectification / Corrective Action” Tab. The “Rectification / Corrective Actions” Tab has three main sections: Rectification/Disposition, Corrective Action and Contractor Responsibilities.
Rectification Disposition Section
This section is designed to clearly provide a clear method for rectification/disposition and then allow the user to further expand and provide relevant details in support of the selected method.
Field |
Required |
Description |
---|---|---|
Method |
Used to classify all available methods for the rectification and disposition of a Non-conformance. This field is populated by a pre-defined list controlled by QAntrol. The options in this field are broad enough to cover all possible methods for rectification and disposition and are:
•Rework / repair to meet specification •Accept as is without repair by concession •Repair with concession •Reject and scrap •Regrade for alternative application. |
|
Rectification / Disposition Details |
Used to provide the details to support the selected method of rectification/disposition. The explanations provided in this field should be framed around the chosen method of rectification/disposition and should clearly support the chosen method. |
Preventative Action Section
This section states the root cause of the NCR and outlines Preventative Actions to prevent re-occurance of the Non-Conformance.
Field |
Required |
Description |
---|---|---|
Root Cause of Non-conformance |
Explanation of the key reason(s) why the Non-Conformance occurred. |
|
Preventative Action |
Outlines preventive measures to be actively employed to avoid a re-occurance of the Non-Conformance. |
Contractor Responsibilities Section
These fields are optional and are designed to assign accountability within the Main Contractor's organisation for the Rectification / Disposition process prior to submission of the Non-Conformance for approval. Not all of these fields may require use and it is recommended that Contractor Responsibilities for sign-off of Non-Conformances be detailed in the Projects Quality Plan.
Field |
Required |
Description |
---|---|---|
Recommended By |
Used to identify the Responsible Person who recommended the proposed rectification / disposition methodology and corrective actions. The date field marks the date the proposed rectification / disposition was completed and is ready for review. |
|
Reviewed By |
Used to identify the Responsible Person for review of the proposed rectification / disposition methodology. The reviewer is generally a Senior Engineer for the Main Contractor. The date field marks the date the proposed rectification / disposition was reviewed and is ready for authorisation. |
|
Authorised By |
Used to identify the Responsible Person for Authorising the release of the Non-Conformance for Approval. The Authoriser is generally the Quality Manager or the Project Manager. The date field marks the date the proposed rectification / disposition was authorised and is ready to be submitted for approval. |